Schools and Universities: Plan Your Summer Renovation Diagnostics Now

Shape

It may be December, but savvy Facilities Directors for school districts are already planning summer renovations. The window for school work is tight—usually just 8 to 10 weeks.

The Pre-Bid Advantage

Don’t wait until June to test the concrete in the gym or cafeteria you plan to renovate. Test it now or during Spring Break.

  • Know the Budget: If the tests reveal high moisture, you can build the cost of moisture mitigation into the RFP.
  • Avoid Change Orders: Nothing kills a school budget faster than an unforeseen $50,000 change order for moisture blocking primer in July.

IFTI’s Education Experience

IFTI has worked with major universities and K-12 districts nationwide. We understand the constraints of the academic calendar.

Do your homework early. Schedule diagnostic testing for your upcoming summer projects.